Tysons/Old Meadow Road Bike/Ped Improvements - Phase 1 in Fairfax County

Lat/Long: 38.916233, -77.217619

    Overview

    Please note: Phase 1 of this project was completed in November 2022. Final design and construction for Phase 2 will occur when additional funding becomes available.

    This project, in cooperation with Fairfax County, built a pedestrian and bicycle bridge and shared-use path in the vicinity of Route 123 and I-495 (Capital Beltway). 

    Based on results of the preliminary engineering phase of the study, and extensive community outreach and input, the Option 2 alignment was selected for final design.

    New bicycle/pedestrian bridge over I-495 and shared-use path from Tysons One Place/Fashion Boulevard to Old Meadow Road/ Provincial Drive

    Phase 1:
    During the first phase of construction, a new bicycle and pedestrian bridge over I-495 was built along with a ten-foot-wide shared-use path from Tysons One Place and Fashion Boulevard to Old Meadow Road and Provincial Drive via the bridge. 

    Phase 2: 
    During the second phase of construction, the shared-use path along Old Meadow Road will be completed from Provincial Drive to Route 123 (Dolley Madison Boulevard).

    Estimated costs

    Preliminary Engineering - $2.3 million
    Right of Way Acquisition and Utility Relocation - $3.1 million
    Construction - $8 million
    Total - $13.4 million

    This project was financed with federal, state and Fairfax County funding.

    Benefits

    The project improves bicycle and pedestrian safety and connectivity in the Tysons area.

    Major milestones 

    • Design Public Hearing - June 2018
    • Environmental Studies Memo Available - August 2018
    • Design Approval - November 2018
    • Begin Right of Way Acquisition - November 2019
    • Advertise for Construction - April 2021
    • Award Construction Contract - June 2021
    • Begin Phase 1 ConstructionAugust 2021
    • Bridge and Shared-Use Path Open - October 2022
    • Phase 1 Ribbon-Cutting Ceremony - November 2022
    • Phase 1 Final Completion - November 2022
    • Begin Phase 2 Final Design and Construction - To be determined as additional funding becomes available

    Other relevant links

    Please note: Phase 1 of this project was completed in November 2022. Final design and construction for Phase 2 will occur when additional funding becomes available. 

    Estimated start date: Phase 1: August 2021 Phase 2 Final Design and Construction: To be determined as additional funding becomes available

    Estimated completion date: Phase 1: November 2022

    Estimated cost of the project: $13.4 million

    Phase: Phase 1: Recently Completed

    Phase 2: In Design

    UPC: 104005

    State ID: I495-029-078, P101, R201, C501, B630

    Tysons Old Meadow Road Bike Pedestrian Improvements - August 2022

    Bicyclist and pedestrian bridge over I-495 (Capital Beltway) - August 2022

    Tysons Old Meadow - December 2021

    December 2021

     

    No videos currently available 

    Last updated: April 10, 2024