Interstate 55 Interchange at Crump Boulevard

Shelby County
I55 and Crump Phase 3A_v15

Interstate 55 is one of the major north-south transportation corridors in the United States. The I-55 Interchange at E.H. Crump Boulevard and South Riverside Drive in Memphis, Shelby County, is utilized by high volumes of a combination of local commuter and through-traffic, including large volumes of commercial truck traffic. The existing interchange cannot handle the current and projected traffic volumes in the area.

The purpose of the proposed project is to improve the I-55/Crump Boulevard interchange by replacing the existing cloverleaf design with a new configuration that reduces crashes, relieves congestion, and provides route continuity for I-55.

Current Status: Tuesday, November 28, at 6:00 AM the below will describe the new traffic patterns. See map above.

I-55 SB outside lane will be closed from the west end of the I-55 Bridge through the project site and the SB inside lane will cross over at the east end of the I-55 Bridge and share the current I-55 NB cloverleaf ramp with I-55 NB and utilize the inside lane of the future I-55 NB from the cloverleaf to the south end of the project.

I-55 NB outside lane of cloverleaf ramp will be closed to allow for I-55 SB use and the outside lane will remain closed to the west end of the I-55 Bridge.

Wisconsin Avenue will be opened.

Crump Boulevard from Kentucky St. to Metal Museum Drive will be closed.

Metal Museum Drive from Alston to I-55 NB will be closed.

Riverside Drive SB will remain closed at Carolina.

Riverside Drive NB will remain closed to Carolina.

Channel 3 ramp to Riverside Drive SB will remain closed.

Channel 3 ramp from Riverside Drive SB will remain closed.

Construction start: 2022

Estimated completion*: 2025

Funding Type: This project is funded with 90% federal dollars and 10% state dollars.

cone
magnifying glass

 

History and Background

The improvements to the I-55 Interchange at Crump Boulevard will be accomplished by constructing new through travel lanes for mainline I-55 traffic, which will eliminate the requirement for interstate traffic to use single-lane, low-speed ramps in order to continue on I-55. A new multi-lane roundabout intersection will be constructed to replace the existing cloverleaf interchange and provide improved access to and from I-55 and existing local roadways.

people

 

Public Involvement and Engagement

Four public meetings/hearings have been held to discuss the I-55 at E.H. Crump Boulevard project as indicated below. The purpose of the meetings was to provide updates on the project, discuss potential construction impacts, and gather public input. A brief presentation was provided at each meeting, followed by Q&A with TDOT representatives.

Meeting

Date

Location

Public Hearing (Draft Environmental Impact Statement)

July 7, 2009

MATA Central Station

Public Information Meeting

June 15, 2010

MATA Central Station

Public Information Meeting

June 1, 2015

West Memphis Civic Center

Public Information Meeting

June 4, 2015

MATA Central Station

In addition to the public meetings, TDOT has held various meetings with public officials and local stakeholders to discuss the project and potential impacts to specific entities.

globe

 

Environment

If remains, artifacts, or other archaeological materials are uncovered during construction, all construction in the area of the find will cease, and the Tennessee Division of Archaeology and recognized Native American tribes will be contacted immediately.

The Tennessee Department of Transportation (TDOT) will no longer pursue the previously proposed long-term (up to 9 months) full-closure of the Interstate 55 (I-55) bridge over the Mississippi River during the reconstruction of the I-55 interchange at E.H. Crump Boulevard. The proposed improvements to this interchange were studied pursuant to the National Environmental Policy Act (NEPA), through the development of an Environmental Impact Statement (EIS), and the option for an up to 9-month full closure of the I-55 bridge during construction was being studied under a supplemental review to that EIS.

In January 2012, the Federal Highway Administration (FHWA) approved a Record of Decision (ROD), concluding the formal EIS development and identifying the Selected Alternative for the reconstruction of the I-55 interchange at E.H. Crump Boulevard. The Selected Alternative involves the replacement of the existing cloverleaf interchange with a new interchange configuration that will provide through lanes for mainline I-55 traffic, eliminating the need for interstate traffic to utilize single-lane, low-speed ramps in order to continue on mainline I-55. A new multi-lane roundabout interchange will be constructed to replace the existing cloverleaf interchange and provide improved access to and from I-55 and existing local roadways.

Following the issuance of the ROD, TDOT determined that a total closure of the I-55 bridge over the Mississippi River (Memphis-Arkansas Bridge) for up to nine months during construction may be necessary. On August 31, 2015, FHWA, in coordination with TDOT, published in the Federal Register a Notice of Intent (NOI) to prepare a Limited Scope Supplemental Environmental Impact Statement (LSSEIS) for the I-55 interchange at E.H. Crump Boulevard Project. The decision to pursue the LSSEIS was based on the potential for significant impacts associated with the potential for a long-term full closure (up to 9 months) of the I-55 Bridge over the Mississippi River during construction. A full closure of the I-55 Bridge for up to 9 months was not previously assessed and disclosed in the approved 2012 ROD or in the subsequent 2015 NEPA Reevaluation.

However, with the removal of this option from consideration, TDOT has determined that there are no changes to the project or any new information or circumstances that should warrant the preparation of an LSSEIS. Therefore, TDOT will cease development of the LSSEIS and instead pursue the development of a NEPA Reevaluation.

The most recent construction plans indicate that the basic setting of the affected environment has not been altered, and the project area is essentially of the same character as previously studied with no substantial modifications in land use or new development. There have been no changes to the project that would alter the findings documented in the approved 2012 ROD.

Record of Decision (ROD) (PDF 395 KB)
Final Environmental Impact Statement (FEIS) (PDF 14.5 MB) 
Draft Environmental Impact Statement (DEIS) (PDF 8.14 MB)

pin

 

Key Project Milestones

Draft Environmental Impact Statement (DEIS) Approved

March 2009

 

 

Final Environmental Impact Statement (FEIS) Approved

June 2011

 

 

Record of Decision (ROD) Approved

January 2012

 

 

NEPA Right-of-Way Reevaluation Approved

Summer 2020

 

 

NEPA Construction Reevaluation Approved

Forecasted for Winter 2021

 

 

Project Letting

March 25, 2022

 

 

Construction

Estimated Completion 1st quarter of 2025

   
paper

Project Contacts

Katie McGinnis (Construction)
TDOT Region 4 District Manager
Phone: 901-475-2519