ADELPHI AREA MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- 95% of concrete slab on grade in building sectors 1A and 1B complete.
- Concrete building foundations at building sector 1A complete.
- Under slab utilities at building sector 1A complete.
- Concrete slab on grade at sector 1A complete.
- Pouring of concrete building foundation footings, piers & walls at building sectors 2G and 2K in progress.
- Rough in under slab utilities at building sector 2G in progress.
30-Day Look Ahead:
- Pouring of concrete building foundations at sector 2G is ongoing.
- Rough in under slab utilities at sectors 2K and 2G to continue.
- Pouring of concrete slab on grade at sectors 2G and 2K is ongoing.
DREW-FREEMAN MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Installation of concrete slab on grade for building sector 1A is complete and 1B is in progress.
- Phase III of the existing building demolition in progress.
- Installation of concrete foundation walls/piers/footings in building sector 2G in progress.
- Rough in under slab plumbing in building sector 2G in progress.
- Rough in under slab electrical in building sector 2K in progress.
- Preparation for structural steel crane set up in progress.
30-Day Look Ahead:
- Continue concrete building foundations for sectors 2G and 2K is ongoing.
- Demolition of existing building Phase III to be completed.
- Rough in under slab plumbing and electrical for sectors 2G and 2K is ongoing.
- Pouring of concrete slabs on grade at sectors 2G and 2K to begin.
HYATTSVILLE MIDDLE SCHOOL
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Sorting and hauling of existing building demolition debris complete.
- Pouring of concrete foundations at building sectors 2K, 2G, and 1A complete
- Concrete slab on grade pours at sector 1A complete.
- Pouring of concrete building foundation footings, piers and walls at sector 1B in progress.
- Construction of site access roads and laydown areas underway.
- Installation of under slab utilities at building sectors 2G and 1B in progress.
- Structural steel deliveries in progress.
30-Day Look Ahead:
- Concrete slab on grade pours at sectors 2G and 2K to continue.
- Under slab utilities at sector 1B to continue.
- Structural steel erection to begin.
KENMOOR MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Concrete building foundations in building sectors 2K, 1B and 1A complete.
- Underground site utilities in building sectors 2K, 1B and 80% of 1A complete.
- Pouring of concrete slab on grade at sectors 1A, 1B, and 2K ongoing.
- Elevator pit including walls, waterproofing and dirt backfill complete.
- Structural steel on site received and shakeout/inventory activities begun.
- Mobilization activities and assembly of the structural steel erection crane complete.
- Grading and setup of staging area for the stability piles on the south side of building complete.
- Site perimeter clearing activities complete.
30-Day Look Ahead:
- Underground building site utilities to be completed.
- Building of concrete foundations at sector 2G and learning stairs to be completed.
- Pouring of concrete slab on grade in sectors 1A, 1B, and 2G to be completed.
- Erecting of structural steel at sectors 1A and 1B to begin.
SOUTHERN AREA K-8 ACADEMY
Project Executive: Arland Knipe
Past Month’s Accomplishments:
- Grading of building pad complete.
- Surcharge dirt loading on building pad complete.
- Temporary power to building pad and construction trailers installed.
- All remaining tree debris removed from site.
- Concrete foundations at East side of building in progress.
- Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
- Installation of MEP under footings and sleeves through foundation walls underway.
- Import of fill dirt and installation of stone for site parking and laydown areas in progress.
30-Day Look Ahead:
- Under slab MEP rough-in at East side to begin.
- Concrete slab on grade at East side to begin.
- Receive deliveries of structural steel to begin.
- Grading site at greenfield areas to begin.
WALKER MILL MIDDLE SCHOOL
Project Executive: Christian Broyles
Past Month’s Accomplishments:
- Concrete foundations at classroom wing 1B complete.
- Removal of surcharge dirt at classroom wings 2G and 2K complete.
- Installation of site haul road and laydown areas in progress.
- First delivery of steel joists and metal deck received.
- MEP underground at classroom wing 1B in progress.
- Pouring of concrete foundation footings, piers & walls at classroom wing 1A in progress.
- Preparing of building pad in Building Wings 2G and 2K underway.
30-Day Look Ahead:
- Classroom wing 1A foundations to be completed.
- Underground MEP at wing 1A to begin.
- Pouring of concrete slab on grade at wing 1B to begin.
- Pouring of foundations at wing 2K to begin.
- Structural steel beams/columns deliveries to be received.
*Please note: Construction timeframes shown above are subject to change.
|