Happy New Year! Welcome to the sixth issue of
PGCPS Blueprint Schools News and Updates!

 www.pgcpsblueprintschools.org
COMMUNITY CONNECTIONS
Pictured (L-R): Harold Beynum (Project Engineer, Kenmoor), Ashanti Hobbs (Project Engineer, Adelphi)
Who doesn’t love some friendly competition? During the holidays, all six Gilbane Construction-Blueprint Schools teams and others within the region competed to see who could gather the most amount of canned goods to give to a Blueprint Schools community. Collectively they donated over 1,000+ lbs. of food to St. Johns Episcopal Church’s Fort Washington Food Pantry, located a short distance from the Southern Area K-8 site. The Walker Mill-Gilbane Construction team came in first with the most amount of canned goods and the Kenmoor team won second place. 

Ashanti Hobbs, Project Engineer for the new Adelphi Middle School, coordinated the holiday giving process between her Gilbane colleagues, stating they were “so excited to not only give but, to connect with people” like they did last October as participants in Hyattsville’s annual Zombie Run.  “Whether it’s the construction of schools or the collection of donations, we're  six different teams working towards the same goal of providing the best for the communities we serve,” said Ashanti. 

 
CONSTRUCTION UPDATES

ADELPHI AREA MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • 95% of concrete slab on grade in building sectors 1A and 1B complete.
  • Concrete building foundations at building sector 1A complete.
  • Under slab utilities at building sector 1A complete.
  • Concrete slab on grade at sector 1A complete.
  • Pouring of concrete building foundation footings, piers & walls at building sectors 2G and 2K in progress.
  • Rough in under slab utilities at building sector 2G in progress.
30-Day Look Ahead:
  • Pouring of concrete building foundations at sector 2G is ongoing.
  • Rough in under slab utilities at sectors 2K and 2G to continue.
  • Pouring of concrete slab on grade at sectors 2G and 2K is ongoing.

DREW-FREEMAN MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Installation of concrete slab on grade for building sector 1A is complete and 1B is in progress.
  • Phase III of the existing building demolition in progress.
  • Installation of concrete foundation walls/piers/footings in building sector 2G in progress.
  • Rough in under slab plumbing in building sector 2G in progress.
  • Rough in under slab electrical in building sector 2K in progress.
  • Preparation for structural steel crane set up in progress.
30-Day Look Ahead:
  • Continue concrete building foundations for sectors 2G and 2K is ongoing.
  • Demolition of existing building Phase III to be completed.
  • Rough in under slab plumbing and electrical for sectors 2G and 2K is ongoing.
  • Pouring of concrete slabs on grade at sectors 2G and 2K to begin.

HYATTSVILLE MIDDLE SCHOOL

Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Sorting and hauling of existing building demolition debris complete.
  • Pouring of concrete foundations at building sectors 2K, 2G, and 1A complete
  • Concrete slab on grade pours at sector 1A complete.
  • Pouring of concrete building foundation footings, piers and walls at sector 1B in progress.
  • Construction of site access roads and laydown areas underway.
  • Installation of under slab utilities at building sectors 2G and 1B in progress.
  • Structural steel deliveries in progress.
30-Day Look Ahead:
  • Concrete slab on grade pours at sectors 2G and 2K to continue.
  • Under slab utilities at sector 1B to continue.
  • Structural steel erection to begin.

KENMOOR MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Concrete building foundations in building sectors 2K, 1B and 1A complete.
  • Underground site utilities in building sectors 2K, 1B and 80% of 1A complete.
  • Pouring of concrete slab on grade at sectors 1A, 1B, and 2K ongoing.
  • Elevator pit including walls, waterproofing and dirt backfill complete.
  • Structural steel on site received and shakeout/inventory activities begun.
  • Mobilization activities and assembly of the structural steel erection crane complete.
  • Grading and setup of staging area for the stability piles on the south side of building complete.
  • Site perimeter clearing activities complete.     
30-Day Look Ahead:
  • Underground building site utilities to be completed.
  • Building of concrete foundations at sector 2G and learning stairs to be completed.
  • Pouring of concrete slab on grade in sectors 1A, 1B, and 2G to be completed. 
  • Erecting of structural steel at sectors 1A and 1B to begin.

SOUTHERN AREA K-8 ACADEMY

Project Executive: Arland Knipe

Past Month’s Accomplishments:
  • Grading of building pad complete.
  • Surcharge dirt loading on building pad complete.
  • Temporary power to building pad and construction trailers installed.
  • All remaining tree debris removed from site.
  • Concrete foundations at East side of building in progress.
  • Monitoring settlement of fill dirt and surcharge dirt on the building pad in progress.
  • Installation of MEP under footings and sleeves through foundation walls underway.
  • Import of fill dirt and installation of stone for site parking and laydown areas in progress.
30-Day Look Ahead:
  • Under slab MEP rough-in at East side to begin.
  • Concrete slab on grade at East side to begin.
  • Receive deliveries of structural steel to begin.
  • Grading site at greenfield areas to begin.

WALKER MILL MIDDLE SCHOOL

Project Executive: Christian Broyles

Past Month’s Accomplishments:
  • Concrete foundations at classroom wing 1B complete.
  • Removal of surcharge dirt at classroom wings 2G and 2K complete.
  • Installation of site haul road and laydown areas in progress.
  • First delivery of steel joists and metal deck received.
  • MEP underground at classroom wing 1B in progress.
  • Pouring of concrete foundation footings, piers & walls at classroom wing 1A in progress.
  • Preparing of building pad in Building Wings 2G and 2K underway.
30-Day Look Ahead:
  • Classroom wing 1A foundations to be completed.
  • Underground MEP at wing 1A to begin.
  • Pouring of concrete slab on grade at wing 1B to begin.
  • Pouring of foundations at wing 2K to begin.
  • Structural steel beams/columns deliveries to be received.

*Please note: Construction timeframes shown above are subject to change.

For questions and inquiries on construction in your neighborhood,
please call (301) 317-6199 or email blueprintschoolsinfo@gilbaneco.com 
Know someone else who would like to receive Blueprint Schools
Program News & Updates
? Tell them to sign up
HERE

For more information about the program, please visit www.pgcpsblueprintschools.com






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Brailsford & Dunlavey · 1140 Connecticut Ave NW Ste 400 · Washington, DC 20036-4014 · USA

Email Marketing Powered by Mailchimp