Project Snapshot
PRISM Project #22-2500 (In Progress)
Wishram Comm. Park Design
    Project Details    
Project Status:  Active since 09/15/2023
Planned Completion:  10/31/2024
This project is in progress. Project scope, activities, and dollars may change.

Project Type:  Planning
Project Sponsor:  Wishram School District
Funding Board:  Recreation and Conservation Office
              Funding  
Planning for Recreation Access: $50,000
Total RCO Grant: $50,000 (100%)
Total Agreement: $50,000 (100%)
              RCO Grant Status  
Total RCO Grant: $50,000.00
Paid To Date: $24,342.20 (49%)
Grant Balance: $25,657.80 (51%)
              Links
 

    Project Description    
The Wishram School District will use this grant to plan for renovation of Wishram Community Park. The school district will hold neighborhood meetings to gain community input to develop planning and 60% design documents for review with Klickitat County. The planning document will be used to develop a construction cost estimate and will help move the project to the next phase. The primary recreation opportunity provided through this grant is passive and active outdoor recreation.

    Project Contacts    
         
Project Sponsor: Wishram School District
  Project Contact: Chris Schumaker
chris.schumaker@wishramschool.org
(509) 767-6090
   
 
Funding Agency: Recreation and Conservation Office    
  Project Manager: Russell Malburg
russell.malburg@rco.wa.gov
(360) 340-1282
   

    Project Location    
County:   Klickitat
Legislative District:   14
Congressional District 2022:   04
Salmon Recovery Regions:   Middle Columbia River
Watershed Administrative Unit:   Celilo
HUC8:   Middle Columbia-Hood (17070105)
WRIA:   Klickitat
Sections:   17
Township:   T02NR15E
Coordinates:   45.65978118
-120.96629684

    Worksites    
Worksite NameScope of WorkProposed Planning Cost
Wishram Community Park (#1) Cultural resources, Engineering/design of recreational facilities, Environmental documentation, Obtain permits, Site master plan development $50,000
 Total$50,000
Amounts may not be complete

    Project Permits    
Permit TypeApplied
Date
Received
Date
Expiration
Date
Permit Number
Cultural Assessment [Section 106]

    Project Milestones    
Milestone NameTarget DateDescription
Project Start 08/01/2023
RFP Complete/Consultant Hired 08/18/2023
Design Initiated 08/31/2023
Progress Report Due 11/21/2023
Annual Project Billing Due 01/12/2024
Progress Report Due 01/31/2024
Draft Design to RCO 03/30/2024
Cultural Resources Study 03/30/2024 Survey required, see special conditions.
Applied for Permits 04/30/2024 Permits initiated
Draft Plan to RCO 05/31/2024
Progress Report Due 06/30/2024
Other 08/31/2024 SEPA/NEPA initiated
60% Plans to RCO 10/01/2024
Final Billing Due 10/15/2024
Final Report Due 10/22/2024
Agreement End Date 10/31/2024

NOTE: This data is subject to change.

    Project Attachments    
Attachment TypeAttachment TitleAttach Date
Agreement - State 22-2500 Agreement - Wishram Comm. Park Design.pdf 09/15/2023
Application Review Report Grant Manager Comments, 22-2500P(compl 11/28/22 21:45).pdf 11/28/2022
Budget Worksheet Wishram Grant Budget Draft.pdf 08/29/2023
Budget Worksheet PRA-BudgetWorksheet+-+Wishram+SD.xlsx.xlsx 11/22/2022
Correspondence Community Input Report-Meeting FINAL.pdf 11/02/2023
Cultural Resource Screening Report Project Cultural Resource Screening Report (09/15/23 13:04:5.pdf 09/15/2023
Letter of Interest PRA-LetterOfInterest+-+Wishram+SD.docx.docx 11/22/2022
Map: Area of Potential Effect (APE) Project APE Report (09/15/23 13:04:51).pdf 09/15/2023
Map: Planning Area Project+Location+Map+-+Wishram+SD.pdf.pdf 11/22/2022
Presentation notes Wishram Park Summary Report-Meeting FINAL.pdf.pdf 11/21/2023
Progress report Progress Report, 22-2500 (accepted 01/09/24 08:08:16).pdf 01/09/2024
Progress report Progress Report, 22-2500 (accepted 11/21/23 14:53:06).pdf 11/21/2023
Project Application Report Project Application Report, 22-2500P (sub 02/21/23 15:27:45).pdf 02/21/2023
Project Application Report Project Application Report, 22-2500P (sub 11/28/22 15:30:05).pdf 11/28/2022
Project Review Comments Proj Review Comments Eval, 22-2500P(compl 02/21/23 15:27).pdf 02/21/2023
Site Plan: Conceptual Site Plan 60 PERCENT.pdf.pdf 01/23/2024
Site Plan: Conceptual Site Plan 30% SUBMITED.pdf.pdf 11/21/2023
Site Plan: Conceptual Site Plan 30% SUBMITED.pdf 11/02/2023
Site Plan: Development site plan Wishram COMBINED.pdf.pdf 01/08/2024