Wishram Comm. Park Design
|
Project Status:  |
Active since 09/15/2023 |
Planned Completion: |
10/31/2024
This project is in progress. Project scope, activities, and dollars may change.
|
Project Type:  |
Planning |
  |
|
Funding Board:  |
Recreation and Conservation Office
|
    Funding |
  |
|
    RCO Grant Status
|
  |
Total RCO Grant:
|
$50,000.00
|
|
Paid To Date:
|
$24,342.20
|
(49%)
|
Grant Balance:
|
$25,657.80
|
(51%)
|
|
    Links |
  |
|
|
The Wishram School District will use this grant to plan for renovation of Wishram Community Park. The school district will hold neighborhood meetings to gain community input to develop planning and 60% design documents for review with Klickitat County. The planning document will be used to develop a construction cost estimate and will help move the project to the next phase. The primary recreation opportunity provided through this grant is passive and active outdoor recreation.
|
County:
|
|
Klickitat
|
Legislative District:
|
|
14
|
Congressional District 2022:
|
|
04
|
Salmon Recovery Regions:
|
|
Middle Columbia River
|
Watershed Administrative Unit:
|
|
Celilo
|
HUC8:
|
|
Middle Columbia-Hood (17070105)
|
WRIA:
|
|
Klickitat
|
Sections:
|
|
17
|
Township:
|
|
T02NR15E
|
Coordinates:
|
|
45.65978118 -120.96629684
|
|
|
Worksite Name | Scope of Work | Proposed Planning Cost |
Wishram Community Park (#1)
|
Cultural resources, Engineering/design of recreational facilities, Environmental documentation, Obtain permits, Site master plan development
|
$50,000
|
| Total | $50,000 |
Amounts may not be complete
Permit Type | Applied Date | Received Date | Expiration Date | Permit Number |
Cultural Assessment [Section 106]
|
|
|
|
|
Milestone Name | Target Date | Description |
Project Start
|
08/01/2023
|
|
RFP Complete/Consultant Hired
|
08/18/2023
|
|
Design Initiated
|
08/31/2023
|
|
Progress Report Due
|
11/21/2023
|
|
Annual Project Billing Due
|
01/12/2024
|
|
Progress Report Due
|
01/31/2024
|
|
Draft Design to RCO
|
03/30/2024
|
|
Cultural Resources Study
|
03/30/2024
|
Survey required, see special conditions.
|
Applied for Permits
|
04/30/2024
|
Permits initiated
|
Draft Plan to RCO
|
05/31/2024
|
|
Progress Report Due
|
06/30/2024
|
|
Other
|
08/31/2024
|
SEPA/NEPA initiated
|
60% Plans to RCO
|
10/01/2024
|
|
Final Billing Due
|
10/15/2024
|
|
Final Report Due
|
10/22/2024
|
|
Agreement End Date
|
10/31/2024
|
|
NOTE: This data is subject to change.